Project cost and control system (PCCS) and primary evaluation technique is earned value analysis (EVA) make use of Project variance analysis reporting (PVAR) reviewing two cycles of the PCCS separately
Planning cycle |
Concerned with budgeting and cost
planning |
|
|
|
|
Control cycle |
Considers
cost monitoring and control including suitable reporting systems |
Cost planning breaking total project down into individual element or work packages and assigning realistic estimate cost. Standard practice to develop cost limits for different levels of work. Cost are then rolled up. Provides a cost ‘map’ for the project
Cost
control ensuring that the cost
limits established by cost play are adhered
to wherever possible.
6
Main stages involved:
1. Monitoring on-going actual expenditure
against cost limits
2. Identifying any variances that occur
3. Identifying the reason for any variances
4. Taking appropriate corrective action
5. Monitoring to ensure that the corrective
action resaves the variance
6. Taking further corrective action as
necessary
Cost planning and cost control function work together but are fundamentally different in approach
Cost
planning essentially a strategic project
function in that it establishes aims and objectives before work actually
starts.
Cost
Control is tactical or reactive function intended to
monitor and control in order to ensure project strategic cost objectives are
met.
Work breakdown structure (WBS) estimated and priced. Sets up a budget plan individual packages have target cost identified by an account code system. Actual cost charged against each packaged related to budgeted costs part of monitoring process. No direct time measurement involved. Time does affect performance of the cost control system regulates the rate of expenditure characteristic of expenditure and projected cash-flow curves.
Time
and cost planning process linked and use the same basic work-package elements
as derived in the initial development of the project WBS
Top
down strategic process, after which three aspects divided and separate,
planning and control systems are developed for the specialized control of each
aspect.
Involves
establishment of cost targets – success criteria. Variance
analysis used determine how close actual
performance is against planned
performance. Deviation from plan
Cost control depends on accuracy of the budget
plan – number of
important prerequisites
Three
primary types of control system
Operates
and different levels,
Low-level process use pre-set information, basis for analysis while higher order systems use more advanced processes main differences between lower and higher order systems lie in:
Low
level cybernetic control is typical for simple response mechanisms
Mid-level cybernetic control more complex or where greater degree of flexibility and response required. Decision making process relies on analysis, case is still directed by analysis but the analysis considers multiple variables.
System includes range of pre-set responses , external factors are also interactive.
Micro computer or advanced processor to
carry out the level of analysis. Much
greater degree of response flexibility than low-level systems. Can only operate within the limits set by
the design of the control system itself.
Only operate within a range of pre-programmed responses
High-level cybernetic control process allow the
system to move beyond any level of pre-programmed response Replaces the database of pre-set responses
with reasoning process are fully interactive. Interact directly with the environment and bypass the reasoning
process.
Human brain uses control systems at all
three levels.
Examples of cybernetic control system as
related to project teams:
1 Lowlevel cybernetic control systems:
• detecting time and cost variances;
• adjusting likely final time and cost estimates to allow for detected variances;
• reprogramming the project schedule following
change.
2 Midlevel cybernetic control systems:
• adjusting estimates to allow for increases in
individual cost rates;
• establishing the individual cost of change
notices and variations;
• allowing the use of provisional and contingency
sums.
3 Highlevel cybernetic control systems:
• generating original tactical solutions to
discovered programming problems;
• updating the risk profile of the project
following change;
• developing a strategy for required
negotiations.
Appropriate
for smaller elements or work packages
Widely
used in computers – ‘yes’ ‘no’ questions. Depending on the answer system directs to
another ‘yes’ ‘no’. process of
elimination
When
faced with complex problem, natural
human reaction is to:
Set
straightforward outcome criteria for individual work packages possible to set:
Analogue
Control system tend to operate where there are
rigidly defined time, cost, and performance limitations
Rigid time limits |
Penalties
related with late completion |
|
|
|
|
Rigid cost limits |
Often
with public works project can be contained with set cost limit |
|
|
|
|
Rigid performance limit |
Quality
of the product is paramount example pharmaceutical research company |
Post-project evaluation and feedback. Involves assessment of completed projects with intention of feeding back any lessons learned to future projects. Essential to learn from past experiences in order to improve future project strategy.
Use of formal reporting system. -Post occupancy evaluation review (POER) review involves detailed evaluation of the finished product including detailed feedback from users.
Number
of important consideration taken into account:
In
addition good control system should:
Cost planning and control system must allow for costs that are likely to be encountered during the course of a project.
Costs
that may or may not be incurred during the project

Fixed and variable cost |
Incurred irrespective of the level of activity Fixed
cost tend to form the major part of projects indirect (or overhead)
costs. Variable costs are those that are incurred at a rate
that depends on the level of work activity.
These are usually direct costs. |
|
|
|
|
Direct and indirect cost |
Direct costs are the costs directly attributable to
the job or project takes- include labour, materials, equipment changes
directly related to carryout the takes.
Indirect cost spread over a project |
|
|
|
|
Measured works |
Backbone
of a cost plan. Work and identify
individual unit prices for carrying out individual sections of work. |
|
|
|
|
Contingencies and reserve |
Allowances
for contingencies in some form of reserve.
Can occur for number of reasons cover undefined additional costs
Amount
of contingency added will depend of many factors including
10%
is not unusual |
|
|
|
|
Fluctuations |
Direct
result of inflation. Easy to predict short-term
rises in labour, material, equipment cost.
Most standard contract allow for a fixed price contract with
fluctuations. |
|
|
|
|
Prime cost and provisional sum |
Sums
agreed or provisionally agreed with specialist or nominated suppliers or subcontractors Nominated
suppliers usually paid through the main contractor payment is identified |
|
|
|
|
Direct payment |
Supply
company carry out their agreed works and invoice the client directly not paid
through the contractor at any time |
|
|
|
|
Bonds and warranties |
Level
of provision required. Bond covers
contractor performance up to practical completion and hand-over Warranty
or guarantee covers the quality and reliability of the finished product after
hand-over |
|
|
|
|
Exchange Rate and currency fluctuation |
Sensible
to pay supply and subcontractor in own currency, estimating to nominate a
project currency using a well-chosen exchange rate |
|
|
|
|
Insurance |
Typical
insurance risks include
Events
that cannot be reasonably foreseen by either party |
Life cycle costs that are likely to affect
the project:
Further ahead you look the more difficult it is to forecast cost of individual element accurately. Greater margin of error cost plan attempts to predict costs in distant future.
Life cycle costing (LCC) process of attaching costs to individual life-cycle stages.
Overall cost incurred in the ownership of a product, structure or system
over its entire life span. Includes costs that have traditionally been
ignored during the planning cycle. It
is long-term strategic cost planning feasibility, conceptual analysis,
development, prototype, design, logistics, support, manufacturing, testing, demolition
and disposal costs.
Decisions made during the early stages of design process invariably have an impact on longer-term performance in the later stages. Running costs and maintenance costs for any mechanical product. Primary objective of LCC to help the project manger and client identify and evaluate the economic consequence of their decisions.
Typical Life-Cycle Phases (6)
Additional Life-Cycle Phases more complex project might include the
following
Most life
cycle costing use common approach set out in the next five steps:
|
Establish the characteristic of the life
cycle. |
Establish cost
for the complete lifetime of the
project. |
|
|
|
|
Build a process cost model |
Incorporate all information known about the processes cost,
functional characteristic of input data, impact on performance |
|
|
|
|
Calibrate the process cost model |
Calibration is the process of adjustment that is necessary in order to ensure model is accurately measuring what it is
supposed to measure |
|
|
|
|
Input all relevant data |
Accurate as the data that is input into
it |
|
|
|
|
Generate a life cycle cost and establish
a strategy |
Life cycle cost profile interpreted and
appropriate strategic decisions. Running cost very high might decide design
changes should take place now, increased development and production
cost. Balance between capital cost
and costs-in-use delicate marketplace trade-off determine by consumer demand |
Number of advantages over traditional cost
planning approaches:
Obvious disadvantages :
A PCCS is a format for the development of cost plans and for mechanisms for monitoring and controlling actual expenditure with
planned expenditure.

PCCS as a
two-cycle system.
|
Cost planning
cycle. |
This includes all aspects of pricing, estimating, establishing targets and
budgets and setting up accurate cost plans. |
|
|
|
|
Cost control
cycle. |
This involves a number of separate phases.
In its most simple form, a cost control cycle contains a work initiation
mechanism, a methodology for observing and collecting cost data from the
system (so that actual costs can be compared with
targets), a comparison system and a reporting system. The
reporting system initiates what is effectively a feedback loop. The report
identifies areas within the project where there are cost problems. This
report then acts as the basis for some form of corrective action. |
Several
cost-control cycle phases are generally recognized:
Phase 1 is cost
planning
Cost control and cost planning are intrinsically
linked
Breaking the
project down into manageable packages, attaching individual budget totals to
these packages based on an estimate of likely costs involved. Cost normally based on some form of
historical or published data.
Two main
approaches should undertake the estimating process:
1.A
professional estimation number of
2. The project
team
Estimating is not
just about cost, linked with characteristics of the project:
Several standard
sources of estimating data
Estimator
classified as follows:
Three generally recognized
stages
Depends on the accuracy of work measurement and reasonableness and accuracy of rate. Estimated costs must be accurate if budget plan to be realistic.
Cost
estimates are prepared first and foremost to calculate the sales price, provide
valuable input into host other activities including
Complexity varies
from project to project, from industry to industry
Senior management setting
the overall project budget by estimating
the overall project costs as well as significant sub project costs

Benefits
of top down estimating:
Disadvantages
of top down estimating:
Relies on budget being developed upwards
from individual activity level, each activity is estimated as accurately as
possible in terms of labour and converted into a financial cost estimate

Benefits
of bottom down estimating:
Disadvantages: of
bottom down estimating
Based on negotiation. Compromise
between top-down and bottom-up estimating. Element and package managers develop detailed action plans and
corresponding estimates for the work responsible. Action plans and estimates to senior management for
approval. End result should be an
action plan and estimate that lies somewhere between the market-driven conservative
estimate of the senior manager and the process-driven generous estimate of the
operational manager.

Benefits of iterative estimating:
Disadvantages: of iterative estimating
Bidding Strategy and Estimate Reporting
Once project or work package approved in principle,
next stage is to prepare the bid for approval by senior management.
Development of bid can be
seen as progression through eight stages:
|
1. Formulate a
viable estimating strategy |
Project schedule and master programme worked out in order ensure
minimum cost meet minimum requirements of success criteria Project work elements for work package, allowance for fees,
overheads, contingencies. Levels of contingencies depend on a number of variables,
more progressed less opportunity for change.
Contingency allowance lower Decision on estimating allowance, standard levels of or
certain variable, pricing labor cost, in-house hourly rate, Estimating process consists largely of calculating the
total number of hours required for each team member and multiplying this by
the agreed unit rate. Estimating and bid form part of an overall costing and
pricing strategy. Initial cost model
and corresponding estimating strategy developed |
|
|
|
|
2. Make initial
(order of magnitude) minimum realistic estimate |
Initial minimum realistic estimate is first estimate based
upon the planning and specification information provided |
|
|
|
|
3. Carry out any
necessary preliminary refinement |
Reducing the percentage
allowed for overheads or contingency, trade-off analysis, develop alternative
cost outcomes by varying the cost-time or cost-performance functions., adjust
risk allowance (risk engineering), lowering the reserves and contingencies,
Insurance risks reevaluated, omitted or reduced. |
|
|
|
|
4. Make realist
(indicative) minimum estimate |
What
the project will cost generally an indicative cost based on the level of
project information available at the time.
Circulated to relevant people.
The minimum realist cost is meant to be an accurate estimate of
package or project will realistically cost, based on the individual costs
involved. Include all direct and indirect costs and all hidden costs. Reasonable provision for contingency and
management reserve, unforeseen events |
|
|
|
|
5. Add for profit
and risk |
Margins to
cover overheads and profit are added.
Minimum profit levels may be set by senior management, Minimum
overheads directly set by company, Risk evaluated separately and would be
quantified as part of refinement process. |
|
|
|
|
6. Compare
overall price to projected cost limit |
Established
cost limit. The overall price
compared with whether competitive.
External applications, limit is not necessarily know, be aware of ballpark
figure. |
|
|
|
|
7. Make
subjective evaluation of bid success probability |
Bid is
considered and decision made proceed or not.
Internal system
– outside the organizational cost limit, decision made not to proceed, look
at way of reducing cost, i.e. reduce resources, increase time limit,
reconsider project logic phase approach, reduce units, External
system – two definite acquisition characteristics 1. type (x)
one-off project little follow-up potential, new-build or one-off
maintenance project complete project at maximum profitability – based on
realistic minimum cost baseline 2. type
(y)
– acquisition related to good chance of more
projects of same type, foothold in client organization so that
more work will follow. – Based on
market forces |
|
|
|
|
8. Develop final
(definitive) estimate |
Final
bid is submitted for consideration by client or by the appropriate approvals
committee |
Assists
in the preparing of estimates and budge plans for projects. Person preparing description of work
measured amount and type cost consultant to scan same quantity information directly
from drawings and into computer

CDES works by linking together several different databases.
Each database contains a different type of information
Description Library |
Descriptions of all different type of work
are broken down with detail accurate pricing 12 Welding 12.1 Arc welding 12.1.1Arc welding, fillet welding |
|
|
|
|
Pricing code and unit rate database |
Works with the description library,
price code individual components preset with appropriate figures, labour,
equipment, material provide time allowance and unit cost. price code might
allow ½ hour per linear meter e.g. Welder: .5 hr /m @ 25.00 /hr = $12.50/m Torch: .5hr/m @ 5.00 /hr = 2.50m |
|
|
|
|
Other database elements |
CDES to digitize drawings (project
statement of work) enter series standard description include quantities work
involved. Produces overall cost
estimate. Allows for Cost Consulting |
Planning cycle includes project cost control system (PCCS) Phase 1, planning process. A(planning and control system) Breaking down the project into separately controllable packages and then calculating a cost target or budget limit for each one. Summarized in the corresponding package total for the next level up. Sum total individual work packages budgets for the whole project. Project budget is another form of project plan. Strategic project plan (SPP) overall strategy is developed from, and includes a number of specific individual plans. Include the Project master schedule (PMS), Gantt charts, and quality plan so on. Project master schedule. SPP also contains project cost plan or project budget/ Project budgets likely to be reviewed in boardrooms in a way time and resource schedules are not. Overall cost performance is perceived as being the single most important performance indicator. Project budget often requires heightened political as well as practical consideration.
Initially project budget is developed from original cost estimates in project proposal, reviewed and adjusted until final version approved authorized limit for spending on project. Modified once the actual costs of various work packages are established.
Sequence of preparation of the Project budget.
Develop ongoing estimated project budget as design progresses
Increasing estimating is carried out using CDES
Report on estimated cost each design reporting stage
Final pre-tender check
Statement of Work (SOW) starting point broken down into WBS that are individually costed / target maximum expenditures.
Cost consultants measure work in project directly from production information. Measurement and quantification in accordance within Standard Method of Measurements (SMM) number of different formats.
Final or baseline budget plan and overall project budget are therefore the end result of a series of internal estimate planning processes. Tempered by external influence of tenders, free to price for work.
Role of Project Budget.
Relates the forecast costs to particular project tasks. Planning management, planning and decision-making tool. May also be used for:
· Baseline for project basis for subsequent earned value analysis
· Developing project cost curves for each element and work package
· Establish reference for variance analysis allowing performance of individual elements and packages to be assessed through course of project
· Moderating spending of element and package managers
· Generate the basic data for scenario analysis in trade-offs
· Estimating likely effects of change notices and variation orders.
Strong psychological effects on project stakeholders. Motivation or demotivating.
Budget Development and Layout
To be effective management tool, the project budget should contain at least:
· Project objectives and activities in terms of measurable outputs
· Financial resources allocated to achieve these objectives and complete activities
· Clearly defined start and finish point of each activity
· Facility to compare actual and planned performance details
PCCS operating cycle referred to as the cost and control system. The operating cycle is the section of the
PCCS that implements the estimating and budgeting
sections of the planning cycle.
Monitors
the actual expenditure against planned expenditure
in order to generate cost variances.
Indicate if project running over or under cost.
PCCS operating cycle comprises four phases
6.3.3.2
Phase 2: Work initiation
To control cost some form of controlled
release of work. Formal issue of a
contract or through change control notices and variation orders or works
order. Project work order (PWO) and
change notice or variation order (VO).
PWO describe work cost centre to
charge, cost accounting codes (CAC) based on project WBS
Variation order and works order document
take numerous form, Cost accounting
codes predetermined and fixed budgets in
order to work these have to be fixed and
can be increased through some kind of formalized control system such as cost accounting
variation notices (CAVNs)
Actual cost data are recorded entered into the system by individual work
packages , data are compared with latest budget
revision and variances are calculated. Cost- data collection process is the
generation of cost variance and schedule variance values. Basis for evaluating performance of project
and perhaps for corrective action
Milestone
Monitoring - EVA is based on milestone monitoring - useful to plot milestone. Budget curve –
simple way to monitor and predict performance trends – simple technique,
disadvantages
Earned
Value Analysis (EVA)
–attractive method of project control because
Earned
value work performed on
project cost project estimator attached to work when project budget was
defined. Term ‘work’ refer to WBS element
separate labour, plant, materials, fuel etc
EVA
is a milestone monitor applied to
Cost
variance difference between budget cost and actual cost value is taken as works
actually completed. Variance expressed
as measurable effort and support effort.
Seven major considerations involved in variance analysis
|
Identify and
validate variance |
Wide
range reason, time dependent good system make allowance for unpaid committed |
|
|
|
|
Quantify
variance |
Allow
variance within pre-set limit without generating alert, only alerts on
significant variances |
|
|
|
|
Determine source
of the variance |
Variance
is significant import to determine causes and effects as quickly as
possible. EVA system able to abstract
data straight forward provided
|
|
|
|
|
Determine
impact of the variance on the project as a whole |
Determine
potential impact negative impact on critical activity more dangerous then
non-critical activity. One variance
requires much more urgent attention than the other |
|
|
|
|
Determine
impact of the variance on other elements and packages |
Review
dependency of delay on another work package, risk exposures,
interdependencies percentages decide on a tactical response to variances. |
|
|
|
|
Determine
the extent to which tactical response is already underway |
Significant
variance usually develop over a period of time current variance is actual
on-going variance that has been identified and addressed. Difficult to remember which variance
occurred previously and corrective measures put in place |
|
|
|
|
Determine
the range of possible outcomes of any corrective action |
Identified
and analyzed reason for variance, determine what corrective actions are available
and what affect these likely to have.
Numerous trade-off scenarios, range of variables Include
|
Earned value analysis make use of the following variables
|
Actual cost
of the work performed (ACWP) |
Actual
cost in terms of payment
or legal committed expenditure incurred in order to get the project to its
current level of development |
|
|
|
|
Budgeted
cost of the works performed (BCWP) |
Some times
known as actual earned value represents budgeted cost that should have been required in
order to get the project to its current level of development |
|
|
|
|
Budget cost
of work scheduled (BCWS) |
Some times
known as planned earned value represents
budgeted cost that should be required
in order to get the project to any specified
level of completion Budgeted
cost multiplied by the works scheduled percentage |
|
|
|
|
Scheduled
time for work performed (STWP) |
Estimated time
required to perform a defined amount of work |
|
|
|
|
Actual time
for work performed (ATWP) |
Actual time taken
to perform a defined amount of work |
|
|
|
|
Cost
Variance (CV) |
Budgeted cost
of work performance (BCWP) minus Actual cost of work performed (ACWP) CV = BCWP – ACWP Comparison of how
much the work has cost in relation to what it was budgeted to cost |
|
|
|
|
Schedule
Variance (SV) |
Difference
between budgeted cost for the works performed (BCWP) minus Budgeted
cost of work scheduled (BCWS) SV = BCWP – BCWS Measures the performance
of the work in relation to budget |
|
|
|
|
Budget at
completion (BAC) |
Sum of all the
individual budgets (BCWS) that make up the whole project. Sometimes known as
project baseline. What the project should cost in total |
|
|
|
|
Estimate at completion
(EAC) |
Estimated total
cost of the project sum of all direct and indirect costs to date plus work
remaining. EAC = ACWP + Estimated (ETC) Updated
estimate of total project cost, sometimes known as planned estimate
approach Expressed as
budget at completion BAC as follows: EAC = BAC – CV Expressed in
terms of cost variance index (CVI): Sometimes
referred to as the current estimate approach |
|
|
|
|
Variance at
completion (VAC) |
Is the difference
between what the project should have cost (BAC) and what is expected to
actually cost (EAC) VAC = BAC - EAC |
Example
of EVA distribution

A variance is any cost or schedule deviation from a specific and predetermined plan. Next stage is to decide how to use them to
define performance and to steer any necessary corrective actions.
Variance and Variance Envelopes
Permitted variances are usually larger in early stages of project, become
smaller as the project progresses. This
is the original of the concept of a variance envelope
Analysis of variance envelope main application for monitoring and control of EVA. Use CV and SV together to show cost and schedule performance of individual WBS to Access performance the two most common are by direct evaluation of the variances themselves or by conversion of variances to indices.
Upper / lower limit 10 – 15% at start of project diminish to 3 – 5% later stages, opportunity for change diminish as details become fixed and not able to change opportunity for change diminishes as a function of time and detail becomes fixed becomes more expensive to make changes and therefore fewer occur.

Variance Interpretation
In general terms:
cost variance (CV) = BCWP − ACWP
Therefore
BCWP > ACWP: work performed has cost less.
BCWP < ACWP: work performed has cost more.
BCWP = ACWP: work on cost plan.
And
schedule variance (SV) = BCWP −
BCWS
Therefore
BCWP > BCWS: works ahead of programme.
BCWP < BCWS: works behind programme.
BCWP = BCWS: works on programme.
These values can also be shown as indices:
Cost Variance Index (CVI) =![]()
so that
CVI > 1.0: good
CVI < 1.0: bad
CVI = 1.0: ok
And
Schedule Variance Index (SVI) =![]()
so that
SVI > 1.0: good
SVI < 1.0: bad
SVI = 1.0: ok
Example interpretations as follow:
CVI > 1.0, SVI > 1
Excellent: project is under cost and ahead on programme
CVI > 1.0, SVI = 1 Good:
project is under cost and on schedule
CVI > 1.0, SVI < 1
Good/Bad: project is under cost and behind on programme
CVI = 1.0, SVI > 1
Good: project is on cost and ahead of programme
CVI = 1.0, SVI = 1
Good: project is on cost and on schedule
CVI = 1.0, SVI < 1
Bad: project is on cost and behind schedule
CVI < 1.0, SVI > 1
Good: caused by faster than expected work practice project is over cost and
ahead of programme
CVI < 1.0, SVI = 1
Poor: project is over cost and on schedule
CVI < 1.0, SVI < 1
Very Bad: project is over cost and behind schedule
Example:

‘alarm’ system that operates in association
with the variance envelope is critical.
Alarm trigger itself often use critical ratio
![]()
The critical ratio uses EVA principles - includes
consideration of both time and cost performance. This means that performance in
one aspect is linked to performance in the other aspect.
Critical ratio will depend on extent to which
the values of each element are greater or less than unity. A good time performance may be associated
with a poor cost performance.
Relative weighting to the time and cost
elements can also be used example
![]()
Critical ratio values are plotted month by month through the project as a curve. Curve dips below unity should evaluate the extent of the deficit and take action appropriate to the magnitude of the problem. Also need to watch value s above unity.

Typical zone
classification:
|
Zone A: Take no
action |
Contains minor negative variations that can be ignored |
|
|
|
|
Zone B: Record and
monitor |
More significant negative variations that cannot be ignored |
|
|
|
|
Zone C: Act
immediately |
Negative variance falls into this zone the performance is critical |
|
|
|
|
Zone D: Emergency response
required |
Negative variance that are super-critical |
|
|
|
|
Zone A1: Observe and
note |
Small positive variances |
|
|
|
|
Zone A2: Investigate
and correct |
Large positive variances · Pessimistic estimating · Poor quality control · Poor supervision · Undetected errors and omissions |
Project
reporting is notoriously deficient for many reasons
In
general reports should:
Timely
well-written reports can:
Routine Reports |
Used
routinely – regardless of project performance
|
|
Development
Review Reports |
When
review of project or development programme,
Detailed
review from time to time to establish developing and establish success
criteria |
|
|
|
|
Exception
Reports |
Highlight
an exception, something out of the ordinary has occurred. Significant
time or cost variance. Subsequent
of exception report would show corrective procedures i.e. exception log,
on-going diary of problem & corrective action |
|
|
|
|
Subject
Specific report |
Specific
aspect detailed monitoring and control required. Such as delays to completion date or critical activity. |
|
|
|
|
Project
variance and analysis Reports (PVAR) |
Use
EVS as the primary analysis tool address full range of relevant information from
routine reporting to monitoring and control of specific problems |
Project variance analysis reporting (PVAR) generated directly from cost data assembled each month. Report variance performance of the project as a whole and then moves down finer levels of detail according to WBS breakdown. Produce CV and SV figures by work package.
Typical PVAR show
· Routine reporting information
· Development progress and review information
· Performance of each level of the WBS in terms of :
o ACWP
o BCWP
o BCWS
o CV
o SV
o EAC
o ETC
· Significant cost or schedule variances
· Sources of such variances
· Reason for such variance
· Proposed responses together with individual responsibilities, action plans and time scales

Each problem cost centre, separate PVAR report generated showing
PVAR
report summarizes performance for project as a whole for each layer of
components WBS element.
May
be illustrated with Earned value performance measure chart

Prerequisites
are:
PVAR
report sometime referred to as the ‘fishing rod’ approach
Project
manager effectively holding the fishing rod adopts the shape and curve of the
ACWP project in.
‘reel
in’ pull rod back horizontally improve efficiency and performance
‘real-out’
level fishing rod less control
Pull
back on rod effect of reducing overall project completion date although end
point of rod may lift (EAC increase)
EAC
reduced need to reel-out allow time
slippage to extend.
Height
of rod decreases the overall EAC decreases
EVA
can quickly and easily calculates