Organizational structure is sometimes summarized in the format of an organizational breakdown structure (OBS)
An organization breakdown structure (OBS) shows the main components of the organization and how they relate to each other in terms of control and communication and any other linkages or connections that cement the various components together.
Project management looks at existing organizational structures, look at proposed or required project structure, adapting and modifying the two structure to produce a new project containing structure
Project teams are therefore established that are
· Wholly internal to the organization
· Wholly external to the organization
· Partly internal to the organization but with external specialist support

Internal project management known as operational or non-executive project management – characteristic of larger organization with constant high volumes of repetitive work
External project management known as executive project management – used by smaller more responsive project teams such as professional consultancies
Project succeed or fail based on people.
Most common project management form is of a project team working within an existing functional organization. The project team draws member from various functional sections and uses them to work on the project until it is completed.
Project
team working within an existing organization structure, once completed project
team disbanded or absorbed back into main organization.
Function of many elements including:
In
functional arrangement, power or status
is defined by a vertical hierarchy through the OBS
Projects are likely to improve systems, procedures, methods or products, and they would tend to be internal rather than external projects. May be established for limited periods in order to address specific demands
Functional
structure common in large organizations typical examples
Typically
of large organizations have continuous rolling
programmes of similar repetitive
or semi-repetitive work.
Benefits
of functional structure:
Disadvantages
of function structure:
The
main drawback with a pure functional structure is the development of operational or organizational islands.
Organizational
Island is a segment of the organization within the overall organizational
structure, tend to act as a semi-independent sector . Control and communication tend to flow down through various
functional divisions. Little communication and co-operation across the
functional divisions, this is inefficient as cross-transfer of co-operation
allow formation of horizontal units.
Self
contained section or unit within an otherwise purely functional structure.
Typically used for projects that are difficult to plan accurately and where resource requirement and provision levels cannot be accurately established beforehand.
Project team disbanded upon completion of its project and individual project team members will return to the pool for use on other projects.
Benefits of Pure project structure:
· System is flexible and responsive to change
· Innovation and evolution are not restricted
· Operational cost quickly adjusted
· Project manger in charge of any particular project is sole charge of project complete authority and control over project resources. No requirement for negotiating with functional manager or project sponsor
· Project staff clear reporting change
·
Communication
lines much shorter
· Informal communication lines shorter develop more quickly and efficiently
· Authority with the project
· Project team member do not have any functional loyalties
· Centralized support much simpler and the overall sizes of support function smaller
·
Easier to incorporate
external consultants
· Possible to execute a series of related projects.
Projects point of view, pure project system appears to be the best supporting structure
Disadvantages of Pure Project structure:
· Several projects running concurrently duplication of effort
· Initial operating costs may be high considerable time before projects completed
· Centralize direction is needed, from of command hierarchy. Higher levels of authority may have difficulty interfacing
· Project mangers (by definition) tend to think ahead
· A sense of competition develop between various project teams
· Project team members tend to have underlying concern about long term commitment
· Project deadlines may create a culture ‘cut corners’; maintain good performance records
· Difficult to compare the performance of individual projects
· Most staff in project structure has some form of original functional specialization prolonged absence from functional section lead to specialization becoming diluted over time.
Compromises between pure project and pure functional forms. It encourages horizontal communication and accountability. Popular structure for organizations undertaking projects. Combines benefits of the functional organization with those of the pure project organization, same time eliminating the disadvantages. Matrix structure is the pure project structure overlaid on the functional divisions.

Main characteristic of an internal project management
structure are:
|
Functional boundaries |
Run vertically through the system, defines the border or line of delineation between the engineering faculty and other faculties act as barrier to communication only gateway is through interfaces |
|
|
|
|
Power or status boundaries |
Run horizontally through the system, represented as a triangle |
|
|
|
|
Organizational islands |
Vertical (functional) and horizontal (power) boundaries |
|
|
|
|
Project sponsor |
Internal system the project manger and the functional manger are both using individual employees as a shared resources. Risk direct competition between the project manger and functional manger over such resources, this conflict can be controlled through a project sponsor – moderator on any potential conflict |
|
|
|
|
The project management chair |
Three different organizational interfaces Project manager – project sponsor (subordinate-boss) Project manager – functional manger (peer-peer) Project manger – project team ( boss-subordinate) |
|
|
|
|
Interfaces |
Horizontal and vertical boundaries act as barrier to communication and co-operation. Interfaces are like gateways through barriers. Tool for control communication – Interface management system (IMS) |
|
|
|
|
Interface management |
Is management of the processes of communication and action across and within the various organizational interfaces. Good communication systems are set up so information flows rapidly and accurately |
|
|
|
|
The process of bidding |
Resource allocation proposal calculate the approximate cost of labour, plant and material required for the project to be executed. |
|
|
|
|
Time recording and
cost-centre charging |
Time spent on individual actives charged to the correct project or functional cost centre |
Good points of an internal project management system
include:
· Project operates as a self-contained unit and project manger has executive control over its operation and development
· Reasonable access to various functional units can access specialist input to the project
· Flexibility and adaptability . respond quickly to change
· Project stays in touch with operational objective of the functional units.
· Internal project management within a matrix structure offers the best of both the project and functional system to some extent
· Effectively spreads the risk between project and functional profitability
· Allows efficient balancing of functional and project resources provided the necessary control systems in place. Resources can be switched between one aspect and the other to absorb changes in demand
· Internal project management promotes innovation and evolution with organization while retaining the functional foundation
Weaknesses of internal project management
· Balancing project and functional responsibilities, conflict can occur where relationship is not so good
· Team member often do not like having two bosses
· Matrix overlap means some responsibilities are effectively shared between the project and functional units
· Project management is complex specialist range of skills, reporting to a project sponsor only makes the job more complex
· Project tends to be depleted of resources toward the end of the implementation life cycle. Make completion very difficult
· Project team member have difficulty re-adjusting to functional units
· Project sponsor introduces new and additional level of authority and control
This type of organization results in the project being spun off as a subsidiary company as it develops.
Choosing the most appropriate structure for a particular project depends on many elements and these should be considered :
External Project teams can be comprised as follows:
External
project mangers more applicable to smaller
organizations with variable workload.
Project manager is the only team lead full authority and control over all components of the project team. Including control and co-ordination of the design team
Number of distinctive characteristics:
|
Multidisciplinary
and shared loyalty group characteristic |
Form of fees
for their external project management system
tend to be strongly multidisciplinary. Susceptible to shared loyalty characteristics, working for his
own practice or company not the same as the objectives of the client conflict
of loyalties between individual parts of the system more susceptible to the
problems of differentiation and sentience than internal project management
teams |
|
|
|
|
Fee
structures |
Open
competitive fee structure, negotiated fee are now generally accepted. Use fee bid package approach Look at a outline
of project make a bid in form of a plan or proposal. Hourly or
percentage basis Typical fee
schedule
|
|
|
|
|
External
contractual linkages |
Wide range of
contractual agreement systems, higher degree of risk of non-performance. Take one of 3
primary forms Completion
contracts – one-off
contract specified goods, service agreed cost by specified date. Term
contracts – long term agreement
agrees to supply good agreed rate to an agreed standard for a fixed term. Service-level
agreement – (SLAs)
where level of service is set rather than the performance. Priced and
arranged in 2 primary ways Competitive
contract – put out
tender Negotiated
contract - not involved
in direct competition, client negotiates price and condition with contractor.
Contracts can
take a number of different forms: Fixed price
contract - cost of
project agreed and fixed in some way in advance Cost or
cost-plus contract -
fixed fees vs. price used insufficient design or product information cost
plus - contract fee is % of overall
cost on final account, Reimbursement
contract. Contractor perform the project at
contractor expense and claim amount plus a fee every month Target Price
contract – target price
plus a fee Contract types
can take number of different forms Standard
forms of contract – Precise
terms & conditions relate clearly to specific performance, aim establish
absolute requirement form completion of the contract - Clauses carefully worded to cover all
aspects of the contract layout established procedures for virtually all
eventualities - Specific provisions within standard forms of contract,
such as direct terms and conditions relating to loss and expense and
extensions of time. -Set out specific level of damages for
non compliance with various events ie late completion -Breaches - Clearly state remedial action
& right in the event of non compliance (damages clause) Professional services contract – implied
terms interpret according to professional body, actual loss incurred
- Damages not set out beforehand &
based on actual loss incurred - Less protection to the client therefore
more risk - Carry professional indemnity insurance
in event of negligence - either state directly or imply a liability for the
consultant to act within the professional standards that are set by the
relevant professional body. - Breaches / negligence or other act
professional failed to act according to standards set out by the professional
body - Most professional bodies produce a book of professional
practice, which lays out the minimum standards and codes of conduct that members
must observe - consultant is commissioned under a professional
services contract that pertains to a given professional body, then any
practice under the contract is deemed to be executed in accordance with that
book of standards typical
contractual links in an external system
Statutory Contracts Health and Safety-Implied common law, contract right or 3rd
party -Maybe formal signed -Heavy favour authority little company do
except comply with requirement i.e. Safety features on machinery must copy
with HSE Proforma Contracts-generally written by one party for
imposition on another party. -Typical examples are contracts for
services by monopoly or near monopoly organisations. -the terms and conditions are largely
written up by the service providers. -The onus of responsibility is therefore
borne by the client. -Very risk clients point of view offer virtually no
protection in the event of a default |
|
|
|
|
External
no-contractual linkages |
Two type of
linkage essential these are authority links and communication links Authority
links – define the power
and control structure that operates with in system Communication
links – Configuration
management system (CMS) define the authority and communication channels
within a project system. |
External project management advantages
Authority |
Pure functional
form traditional reporting structure clear line of authority running down
through the structure. |
|
|
|
|
Communication
|
Easiest in
functional structure but informal communication encounter blocks. Authority boundaries may restrict both
formal and informal vertical communication Matrix structure reduces blocks formal
cross-function communication . pure project
structure greatest use of informal
communications offer flexible communication solution |
|
|
|
|
Knowledge
transfer |
Easiest type of
knowledge to store and use in future
operation. Matrix
structure allows function knowledge to be used in project Pure project
tend to be restricted to areas of commonality between individual projects |
|
|
|
|
Loyalty |
Functional
structure develop greatest individual loyalty - career progression with functional section Matrix
structure loyalty shared individual project team member |
|
|
|
|
Technology |
Functional tend
to rely on existing technology to manufacture or produce something Matrix
structure - likely to use existing technology to innovate in addition
generate new technological innovations Pure project
greatest demand for innovation technology |
|
|
|
|
Cost |
Pure functional
structure - large fixed cost inflexible to changes in workload and structure Matrix
structure more flexible increase or decreased size depends on workload
variations Pure Project – most
flexible approach can produce the lowest running costs |
|
|
|
|
Co-ordination |
Pure Functional
structure – most formal reporting system co-ordination low Matrix generate
higher co-ordination demand enhanced co-ordination is necessary because
project run across functional boundaries and potential for destructive
competition and conflict increase Pure project –
requires similar high levels of co-ordination in order to avoid the
possibility of duplication of effort. |
|
|
|
|
Support
functions |
Pure functional
structure require well-developed centralized support functions functional manger concentrated on
functional objectives in the knowledge decentralized support is areas such as
it admin Matrix
structure –similar requirement but some level of support may be devolved to
individual project mangers large projects own administration and IT support Pure
project may require little or no
centralized support |

A pure
functional organizational structure should be chosen in the following
circumstances.
A matrix
organisational structure should be chosen in the following circumstances.
A pure
project organisational structure should be chosen in the following
circumstances.




Association
for Project Management (APM) in UK is part of the International project
management Association (IPMA) and strong links to similar international bodies
.
APM
established a Body of Knowledge(BoK) that act as a standard for evaluated
project management expertise and is a self assessment tool for project manager
to measure their own professional competence for different levels of membership
The
Stated aims and objectives of the APM are:
To act as first point of contact |
National
authority through internet |
|
|
|
|
To lead the
development of professionalism |
Further project
management practices |
|
|
|
|
To Champion
interest representation |
Represent
interest of UK project management in all sections of industry |
|
|
|
|
To establish
standardization of qualifications |
Standardize the
academic and professional qualification / certificated |
|
|
|
|
To develop a
functioning national branch network |
Establish and maintain
national branch network to facilitate participation |
|
|
|
|
To establish
practice and procedures for training |
Establish and
maintain ongoing training programs |
Body of Knowledge (Bok) establishes national guidelines and standards for the profession, and is one of three levels of standards that are required for an effective project management system it has four primary areas qualified project manager must have relevant academic and experiential ability
Project Management |
Includes
specific aspects of understanding of project life
cycle, project strategy and
project environment understanding of
wide range of issues that relate to project management practiced |
|
|
|
|
Organization
and people |
Include leadership, communication and team building, Leadership style has to evolve
as the project develops |
|
|
|
|
Techniques
and procedures |
Scheduling and estimating,
planning, understand various control and
monitoring procedures, latest approaches to planning and control
earned value that link one or more success criteria variables |
|
|
|
|
General
Management |
Finance and law, basic understanding of
procedures and approaches involved, basic
contract law recognizes actions not
permissible under terms and condition of contract. |
BS6079 is the British Standard guide to project management. Establishes guidelines and procedures for project management in the UK. Important single section is the standard strategic project plan (SPP) it is based on standardization. There is no standard requirement for document preparation, recording, cost planning and control or even of quality control . Projects are set up and executed in numerous ways.
Generic
project plan applied to all projects
BS6079 SPP is a standard document operates at one level within project management, run in conjunction with the standards established by the professional association and institution and also in conjunction with sector – or company-specific standards
Main element of the generic SPP
|
Project aims
and objectives |
Section
for project aims, objectives clearly stated, objectives relate to time, cost,
quality and a range of other objectives clearly defines everybody involved
clear terms of reference to work to. Sub objectives
run in parallel with the project objectives and carry equal importance may
require different planning and control techniques. |
|
|
|
|
Subject
specific sections |
BS6079 gives a
proposed numbering system for information
presented under each heading.
Laid out in the same way and each subject specific heading should address
the same issues and present information in the same format. Specific sections for scheduling and cost control
original plans and update and separate section maintained for the effects of
change. Project History or diary, record all important
communication events that occur during the course of the project, audit trail
should the need arise, repository information for subsequent use in
post-project review |
SPP
contains all relevant project information acts as both a record document and as
a benchmark for project as originally developed and planned. Project progress and designs plans are
implement, SPP updated .
Typical
contributors to the SPP are:
Assembled
to a specific timetable, include all necessary project design and specification
information.
National
standard for project management practices, it acts as a benchmark particularly
in relation to standardizing procedures and documentation. Most import single standard document within
BS6079 is the strategic project plan (SPP).
Allows establish all projects in same basic
format
Project management IN a Controlled Environment, version 2 (PRINCE2) is a methodology that covers organization, management and control of projects. Introduced in 1996 original PRINCE first developed by the Central Computer Telecommunication Agency (CCTA) in 1989. Intended for UK government standard for IT project management.
Based on a process model for a project breaking project down into component processes. Each process is then defined in terms of its key inputs and outputs, and in terms of aims and objectives for each process, based on the life cycle of the project, each component evaluated and analyzed separately. Allows more efficient use of resource and accurate measuring of progress.
Main advantages offered by a PRINCE2 approach are:
· Offers a standardized project structure with clear start, middle and end
· Allows regular and detailed reviews of actual progress against planned progress
· Allows regular and reviews of actual progress against the business case
· Identifies and makes use of flexible decision points
· Identifies and allows automatic control of any deviation from the project plan
· Ensures that the timing of involvement of management and stakeholders is optimized during the life cycle of the project
· Encourages and develops good communication channels between the project, project manager and the rest of the organization.
Highlighted some of the primary standards that apply to project management practice, Project management highest level is International Project Management Association (IPMA) global body for project management practice. Attempt to establish and standardize areas of expertise that are required by practitioners in the respective countries.
Level
which standards used depend on individual company polices and level of adoption
for standards by professional practices.