Updates as of Nov
25, 2000
see July 22, 2001 further down
see Feb 4, 2002 further down
see Mar 06, 2002 further down
1- We have produced a pre-production prototype.
This is a complete redesign following the field tests of last year and
described in this technical documentation. The main new features are:
3- We are close to make a deal with 2 large companies. This will enable to firstly do a field test with the 200 units in a Toronto building (1 full floor of offices). Hopefully the companies will invest the funds required to mount a full production line.
4- If by January 2000 we have not closed the deal, we will go out to smaller private investors to raise the funds for the production to reach 5,000 units. Later we will IPO to escalate to full production expected in the range of 50,000 units for the first year.
5- Our business plan is now mature.
6- We have received the US patent, and we have filed for international patent.
7- We have now an expert outside evaluation of our patent.
Update as of July 22, 2001
1- The pre-production engineering prototype has been tested extensively specifically for life testing. We found some concerns and we redesigned the power unit. In the process we achieved the following improvements:
The picture shows the prototype
unit in a typical fixture.
Details of Line connection to the Dim&Save Power Unit
Update as of February 4, 2002
Due to delays and problems in production, the pre-production units came in only mid December. And because of the Christmas Holidays, it took us some time to fully test all units. Unfortunately we had to modify the units slightly (and reprogram the microprocessor) because we found that the previous version was too sensitive to ballast and tube combinations. We have now fixed that problem, and the units all perform better than expected.
We have re-designed also a zone controller which is not tube/ballast sensitive, and requires very simple initial auto-calibration.
We have 30 units mounted in fixtures, and they all have undergone heat testing and dim cycling extensively. They have been shipped to be installed in a building in Toronto.
Update as of March 06, 2002
The units are now installed and
are under Beta testing:
Each zone controller is controlled by a central PC which has a light management program, with a programmable lighting profile. For instance:
power is provided by the building management program to come on a 6am and off at 10:30pm
The software
management of the floor is set for an initial trial basis:
6:30 to 8:00 60% power
8:00 to 9:00 70% power
9:00 to 17:00 90% power
17:00 to 10:30 50% power (cleaning staff)
On Sundays/Saturdays and Holidays and during the night, power is set at 70% if the building power comes on demand.
(this is only one scheme but is not optimized).. We are trying to obtain the reaction of the occupants who were not told of the dimming actually taking place. So far no one has actually noticed any change in lighting !!!!!
The next phase is to tell them,
and ask them to manage the blinds in such a way that major savings could
be obtained during clear days. The units can be dimmed as low as 30% each.